PRQ
betaThe register, Monte Carlo engine, correlation between risks, sensitivity tornado, funded percentile chooser, and the PDF report with its methodology annex are all live today. Beta means the surface is still moving, not that the numbers are provisional.
Project
Risk register
4 risks · 4 active in the simulation
| Risk | Category | P(occur) | Impact distribution | |
|---|---|---|---|---|
| Operational | 30% | tri$50,000/$120,000/$350,000 | ||
| Schedule | 50% | pert$75,000/$200,000/$500,000 | ||
| Technical | 10% | tri$200,000/$600,000/$1,500,000 | ||
| Regulatory | 20% | pert$30,000/$80,000/$250,000 |
Simulation
10 000 is enough to stabilise P50 / P80 / P90 on a register of this size. Bigger runs tighten the tails.
Same seed, same figures — for runs that need to be reproduced exactly.
This simulation assumes no correlation between risk items. Positively correlated risks will produce understated tail outcomes.